Has anyone succeeded in processing the data from REACH/Reach RS to Trimble Total Control or Trimble Geomatic Office or Trimble Business Control?

Can you please share me the data and report your processed?

of course. send me your email, please. i´m a new user and can´t send atachments…

my email is ytuanadatu@gmail.com, please provide the raw data un ubx format and your step by step procedure. I would like to replicate the processed. Thanks!

Hello Yasser, if you have received that email. Please can you share it with the community to avoid same question from other members.

Thank you

Unless you want bots to collect your email and spam the heck out of it etc, you might not want to make (edit) your email public or modify it in code. I.e blahblah AT gmail DOT com. Bots probably got that figured out as well though.

Waiting for an answer

the process shared by evandro was sent already in your email.

Hello sir @Yasser_Arafat_Tuanad , I am experiencing this problem now. TBC can’t read my RINEX 3.03 directly exported from Reach view. I am counting on you, hope to hear from you soonest.

Kindly provide your email. so i can sent the step by step procedure. Thanks

Kindly find the attached file.Step by Step procedure is TBC 01-TBC 09.
.

2 Likes

You could send me the step by step to my mail please, I am interested in how you pass the EMLID files to rinex, or what version of Rinex you use to read them directly in TBC, in advance thank you very much and sorry for my english is just google translates
luck

1 Like

sorry
my mail hdiazs@gmail.com

Here’s my email sseradscic@gmail.com, thank you!

I’m having this prob as well. TBC can’t read my RINEX 3.03 w/c is downloaded directly from the device.

You can directly import any rinex version to TBC. but mostly the rinex generated by emlid does not show automatic in the project when you import it. You must chect the point and rename it. Then, it will appear in the TBC Project plan. You can sent me also your rinex so i can try it…

You can directly import any rinex version to TBC. but mostly the rinex generated by emlid does not show automatic in the project when you import it. You must chect the point and rename it. Then, it will appear in the TBC Project plan. You can sent me also your rinex so i can try it…

Hi I try to do it but i could’nt when I import the rinex files don’t show me the start and end time (see the print screen)
Can you help me please, i doing something wrong??

Agustin,

To get the times, you need to review the updates of the TBC (Support_check for updates), after that, the start and end times appear.

To give you a fixed solution, besides importing the observation files, you also import the efemerides files and you’re done.

Regards,